Construction update in Quartier Cavendish development

Here is some news on construction in the Quartier Cavendish development, much of which is my own District 2.  Councillor Glenn J. Nashen's District 6 covers the properties on Kellert.

The 68 townhouses and 16 semi‐detached homes are now all complete.

There are 31 single family homes: 24 are completed, with minor finishing touches/landscaping outstanding on some; four others are under construction and progressing well; one lot has been approved in principle and construction should begin in spring 2017; and two lots still face a design review from our Planning Advisory Committee (PAC) and must then go through the permitting process.

BSRCavendish

The mixed use building under construction on The Avenue.

The mixed use building of 90 units on six stories, plus a penthouse and some commercial establishments on the main floor, is moving along. The underground parking structure is complete while the back filling of the foundations is also nearly done. The builder, the BSR Group, plans on continuing construction through the winter in hopes of completing this project by the end of summer 2017. Our Urban Development Office continues to work closely with the builder to keep some nuisances to residents of Park Place to an absolute minimum.

In our year end permit statistics, we experienced yet another surprisingly big year of construction in the city. While we were expecting 2016 to be busy, construction estimates for 2016 were actually the second highest in our history (over $60 million  behind only 1987, a year when several high rise towers began construction in the same year). These numbers are compiled from estimated construction costs before projects begin (at time of permit issuance) so they are only estimates, but they are an accurate indicator of how much construction is taking place in our city. Permit fees are based on this estimated value and is therefore linked directly to generation of revenue for the city and this list does not include “smaller” permits such as tree cutting permits, tempos and signs. Promising news for certain.

Related

The Equinoxe rental condos have been sold

The Equinoxe apartments on Marc Chagall Avenue in...

Gardens of Distinction program replaces Maisons Fleuries/Le programme Jardins d’exception

The Maisons Fleuries program has been a mainstay in...

The future of Quartier Cavendish: information meeting hints at highrises and a hotel

How does the Hilton Quartier Cavendish sound? Could a hotel...

Public Safety Station will not be placed at the corner of The Avenue and Park Place

The long awaited first Public Consultation meeting for the...

Newsletter

Don't miss

Our local MNA gives us hope that Pablo Rodriguez can win the next election

The province of Quebec has never been in worse...

David Tordjman has won the Côte Saint-Luc election for mayor

Across Quebec, including of course Côte Saint-Luc, municipal elections...

The Equinoxe rental condos have been sold

The Equinoxe apartments on Marc Chagall Avenue in...
Mike Cohen
Mike Cohenhttps://mikecohen.ca
Mike Cohen, born and raised in Côte Saint-Luc, has long been active in the community as a volunteer, journalist, and consultant. He attended local schools and was first elected as City Councillor for District 2 in 2005. Since then, he has been re-elected in each municipal election, most recently in 2025.

Our local MNA gives us hope that Pablo Rodriguez can win the next election

The province of Quebec has never been in worse hands than the CAQ government. Premier François Legault does indeed seem to be the captain...

David Tordjman has won the Côte Saint-Luc election for mayor

Across Quebec, including of course Côte Saint-Luc, municipal elections were held on Sunday, November 2. Lior Azerad in District 5 and...

From The Montrealer Newspaper: Table 51’s Laval revamp, Maiko Sushi, Yans Deli & a new Ben & Florentine

Table 51 Restaurant  and Bar made its debut at Carrefour Laval in 2010,  branching out to add a Decarie location next to old Blue...