Phase Two of the City Hall/Library Parking Lot project will be paved soon

As Phase Two of the City Hall/Library Parking Lot project is under way, we have been getting questions regarding the pedestrian access to the building.

For this week, pedestrians are being directed to the temporary stone path that runs from Sir Walter Scott to Cavendish, on the south side of the parking lot.  The contractor will be bringing more signs to direct the pedestrians from the back of the lot towards this path.  He has also adjusted the temporary fence and its supports following a complaint received about a possible tripping hazard risk.  
 
Weather permitting, we expect that Phase Two of the parking lot should be paved by September 1.  This will provide parking in the area that is presently under construction and the sidewalk for pedestrian access towards the back entrance.  The contractor has been advised that this sidewalk closer to the building is a priority and he is working to see if it can be done sooner than later.
 
The entire project should be completed by October.
MeetingParklot

Residents take part in a meeting about the parking lot construction.
 
Last week we invited area residents to City Hall to get a closer look at exactly what this project will look like upon its completion. I met with a number of residents from Marc Chagall and Sir Walter Scott. There was a request for us to save even more trees than originally planned. We have done so and as a result there will be eight less new parking spots than originally envisioned.

Related

Newsletter

Don't miss

D’Arcy McGee Medals handed out; Remise de la Médaille de la citoyenneté D’Arcy-McGee

The  11th edition of the D’Arcy-McGee Citizenship Medal ceremony...

Bialik students complete Traffic Study

I recently assigned my team of  Bialik High School...

District 2 Walk: Taking the Pulse of the Community

On Monday, June 8, I conducted a formal District...

A change in format for my annual District Town Hall

Ever since I was first elected as the city...
Mike Cohen
Mike Cohenhttps://mikecohen.ca
Mike Cohen, born and raised in Côte Saint-Luc, has long been active in the community as a volunteer, journalist, and consultant. He attended local schools and was first elected as City Councillor for District 2 in 2005. Since then, he has been re-elected in each municipal election, most recently in 2025. Mike Cohen, né et élevé à Côte Saint-Luc, est depuis longtemps actif au sein de la communauté en tant que bénévole, journaliste et consultant. Il a fréquenté les écoles locales et a été élu pour la première fois conseiller municipal du district 2 en 2005. Depuis lors, il a été réélu à chaque élection municipale, la dernière fois en 2025.

D’Arcy McGee Medals handed out; Remise de la Médaille de la citoyenneté D’Arcy-McGee

The  11th edition of the D’Arcy-McGee Citizenship Medal ceremony took place June 18 at the Côte Saint-Luc Aquatic and Community Centre, presided over by...

Bialik students complete Traffic Study

I recently assigned my team of  Bialik High School student  interns to conduct a small survey related to traffic  patterns in the areas of...

District 2 Walk: Taking the Pulse of the Community

On Monday, June 8, I conducted a formal District 2 Walk, a new variation of the Town Hall meetings I have been holding for...

1 COMMENT

  1. If you have some problems with the project you can find project experts that will help you to complete the entire project. For example, I use professional service if I have some problems with academic writing assignments.

Comments are closed.