Compromise on Marc Chagall construction almost reached

Weekend work has resumed for the time being on Marc Chagall Avenue for the first phase of two 12 storey apartment buildings to be known as the Equinox. As noted many times, this land has been zoned for a highrise for 29 years.

City council will hold a special meeting on Monday evening, May 29, to adopt amendments to our noise bylaw and establish new hours of work for construction. Since both the city and the developers wish to avoid a legal fight in court, negotiations have been taking place over the last several weeks in order to arrive at a compromise.

Constructionssite

More than a month ago, when I learned that the developers intended on working weekends and weeknights, I established a committee with representatives from the five condominium associations directly affected by this work: Rothchild I and II, the Marquise, the Bellagio and Les Cours Marc Chagall. Last week we met with the developers and while the official compromise must still be finalized by legal counsel, their plan appeared to be acceptable to everyone in the room.

In an ideal world, there would only be construction weekdays until 5 pm and not on weekends at all. The developers are on a tight schedule as they wish to have their first building ready for occupancy on July 1, 2018 to correspond with the most standard leases. They have agree to slow down their work considerably and only have some units available at this time as the message I have received loud and clear, particularly from the two Rothchild buildings,is that they do not wish to hear construction noise seven days a week. There are others, I must tell you, who would like to see this work finished as soon as possible irregardless of how many days they work.

The developers will need to work weekends through at least June 15, after which point the schedule will slow down and they will only need 50 percent of the Saturdays. On issues of safety, street cleaning, parking  and other types of noise disturbances,  discussions are moving along nicely,

I will continue to provide updates, with certainly much more to say after May 29.

 

Related

Newsletter

Don't miss

A change in format for my annual District Town Hall

Ever since I was first elected as the city...

The 2026 Côte Saint‑Luc Golf Classic set for July 7 at Meadowbrook Golf Course

The City of Côte Saint‑Luc will host the 2026...

Temporary stop sign on Kildare and Rembrandt a relief during  Hydro work

With Hydro-Québec's major infrastructure work on Merrimac Street and...

The Côte Saint-Luc Master Plan has been adopted and I support it

On Monday, May 11  four and a half years...
Mike Cohen
Mike Cohenhttps://mikecohen.ca
Mike Cohen, born and raised in Côte Saint-Luc, has long been active in the community as a volunteer, journalist, and consultant. He attended local schools and was first elected as City Councillor for District 2 in 2005. Since then, he has been re-elected in each municipal election, most recently in 2025. Mike Cohen, né et élevé à Côte Saint-Luc, est depuis longtemps actif au sein de la communauté en tant que bénévole, journaliste et consultant. Il a fréquenté les écoles locales et a été élu pour la première fois conseiller municipal du district 2 en 2005. Depuis lors, il a été réélu à chaque élection municipale, la dernière fois en 2025.

A change in format for my annual District Town Hall

Ever since I was first elected as the city councillor for District 2 more than 20 years ago, I have held regular Town Hall...

The 2026 Côte Saint‑Luc Golf Classic set for July 7 at Meadowbrook Golf Course

The City of Côte Saint‑Luc will host the 2026 Golf Classic on Tuesday, July 7, 2026, at Meadowbrook Golf Course, 7001 Côte Saint‑Luc Road....

Temporary stop sign on Kildare and Rembrandt a relief during  Hydro work

With Hydro-Québec's major infrastructure work on Merrimac Street and part of Kildare Road expected to continue through the end of August, I wanted to...