Urgent work will cause road disruptions on Marc Chagall Avenue and Kildare Road

Urgent work by Hydro-Québec and Bell Canada will cause significant inconvenience to motorists on Marc Chagall Avenue and Kildare Road near Cavendish this summer.

I met with some members  of our Urban Planning team today and the city has no choice but to issue the permits now as both Hydro and Bell insist the work cannot wait without potential negative repercussions for residents.

Hydro-Quebéc will be performing urgent work to demolish and rebuild their access point at the corner of Mackle and Marc Chagall. This work is necessary for the residents in the sector to have functional electricity and HQ is sending out letters to residents explaining the importance of this work. It will commence on June 25 and last until at least September 20. The timing could not be worse, with construction for Phase Two of the Equinoxe high rise buildings now at the cement pouring stage. That job won't conclude  until next June. We asked Hydro if there was any way to delay this work and they stated that residents could be at risk of major power outages .
 
Here is the signage plan.
Signalisation NRC
 
Urban Planning and Public Security will try to manage this the best possible way. More information on the rerouting of traffic will be forthcoming,
 
Meanwhile, Bell will be digging up Kildare (between Rembrandt and Cavendish) during weekends beginning soon to upgrade its network in the area. You may have noticed a lot of Bell repair trucks in the area in recent years. Traffic will be diverted into two lanes. It was timed to begin once school concluded at JPPS-Bialik.
 
 
 
 

 

 

Related

Hydro-Québec meeting at City Hall March 30 pertinent to many District 2 residents

There will be a Hydro-Québec information session on...

Aging substation  makes us vulnerable for more power outages

Last week I wrote a blog, previewing the major...

Newsletter

Don't miss

A change in format for my annual District Town Hall

Ever since I was first elected as the city...

The 2026 Côte Saint‑Luc Golf Classic set for July 7 at Meadowbrook Golf Course

The City of Côte Saint‑Luc will host the 2026...

Temporary stop sign on Kildare and Rembrandt a relief during  Hydro work

With Hydro-Québec's major infrastructure work on Merrimac Street and...

The Côte Saint-Luc Master Plan has been adopted and I support it

On Monday, May 11  four and a half years...
Mike Cohen
Mike Cohenhttps://mikecohen.ca
Mike Cohen, born and raised in Côte Saint-Luc, has long been active in the community as a volunteer, journalist, and consultant. He attended local schools and was first elected as City Councillor for District 2 in 2005. Since then, he has been re-elected in each municipal election, most recently in 2025. Mike Cohen, né et élevé à Côte Saint-Luc, est depuis longtemps actif au sein de la communauté en tant que bénévole, journaliste et consultant. Il a fréquenté les écoles locales et a été élu pour la première fois conseiller municipal du district 2 en 2005. Depuis lors, il a été réélu à chaque élection municipale, la dernière fois en 2025.

A change in format for my annual District Town Hall

Ever since I was first elected as the city councillor for District 2 more than 20 years ago, I have held regular Town Hall...

The 2026 Côte Saint‑Luc Golf Classic set for July 7 at Meadowbrook Golf Course

The City of Côte Saint‑Luc will host the 2026 Golf Classic on Tuesday, July 7, 2026, at Meadowbrook Golf Course, 7001 Côte Saint‑Luc Road....

Temporary stop sign on Kildare and Rembrandt a relief during  Hydro work

With Hydro-Québec's major infrastructure work on Merrimac Street and part of Kildare Road expected to continue through the end of August, I wanted to...