Yesterday, Thursday, July 15, 2010, the contractor hired by the City of Côte Saint-Luc was conducting excavation work to replace the underground aqueduct in the area on Kildare Road, close to Merrimac. Before conducting such work, it is common practice to request confirmation from the utility companies indicating if there is any underground equipment located at the targeted area of the work site. 

Hydro-Quebec advised the contractor in writing that they had no underground equipment in the area in question. Unfortunately, it turns out the information was incorrect and there was indeed underground equipment at this work site. As a result the contractor cut a supply line which led to yesterday’s power failure.   

In the event you have a claim to make with respect to the power failure it must be received by Hydro-Quebec by July 29, 2010 and should be directed to Hydro Quebec as follows:   

By mail to:        HYDRO QUEBEC DEPARTMENT OF CLAIMS 
CP. 11003 – Succursale Centre-Ville 
Montréal, Québec 
H3C 4T3 

By Fax:                    HYDRO QUEBEC DEPARTMENT OF CLAIMS 
1-888-558-7879 

While the City of Côte Saint-Luc was not responsible for the power failure itself we had a responsibility to communicate with you in a more effective manner yesterday.     

The City of Côte Saint-Luc prides itself on its excellent customer service. The level of communication in this instance was not up to our standards or the standards we expect from contractors. In order to ensure that this lack of communication does not occur again (specifically in your area during the remainder of the construction schedule), the City will be taking appropriate action to ensure that we and our contractors communicate with you effectively. 

The City of Côte Saint-Luc is committed to the health and safety of its residents. Under normal circumstances in the event of a power failure lasting as long as the one of yesterday, the City would have provided you with various amenities (i.e. bottled water, opening a suitable shelter, having personnel on site to answer your questions). We regret that this did not occur. 
To ensure your safety and wellbeing during the balance of the work being done in your area, the City has taken the following measures: 

·        In the event a situation arises and residents contact our 24 hour dispatch service at 514-485-6960, appropriate city personnel will be notified and assigned to the situation as appropriate. 
·        Our Manager of Customer Service for the Public Works and Engineering Department, Beatrice Newman, is available to take your comments by phone at 514-485-6800, ext. 3002 or by email at bnewman@cotesaintluc.org 
·        We will be in close communication with the contractor and the utility companies, in the unlikely event that another incident arises, to take immediate action. 

We hope that this letter gives some comfort to you that the City is taking this matter very seriously and will do everything we can to improve our customer service during the duration of the construction work. Please accept the enclosed gift certificate as we know yesterday was a difficult day for you. 

Sincerely, 
 
Anthony Housefather                                Mike Cohen 
Mayor                                                Councillor, District  2

Related

Rembrandt Park Report Card Ahead of the Summer Season/

With Thierry Dhaisne and Jordan Guetta.   Last week I met...

Ilan Ramon plaque returned to its proper place in Côte Saint-Luc

Ilan Ramon was the first Israeli astronaut on the...

Three generous donations give a boost to the Côte Saint-Luc Cats Committee

I would like to provide an update on the...

The Côte Saint-Luc Cats Committee has an uncertain future

Some 15 years ago a lover of cats named...

Newsletter

Don't miss

Pablo Rodriguez gave us hope and then the Quebec Liberal Party imploded; can they bounce back?

The province of Quebec has never been in worse...

David Tordjman has won the Côte Saint-Luc election for mayor

Across Quebec, including of course Côte Saint-Luc, municipal elections...

The Equinoxe rental condos have been sold

The Equinoxe apartments on Marc Chagall Avenue in...
Mike Cohen
Mike Cohenhttps://mikecohen.ca
Mike Cohen, born and raised in Côte Saint-Luc, has long been active in the community as a volunteer, journalist, and consultant. He attended local schools and was first elected as City Councillor for District 2 in 2005. Since then, he has been re-elected in each municipal election, most recently in 2025.

Côte Saint-Luc City Council and our new mayor begin our mandate/Le conseil municipal de Côte Saint-Luc et notre nouveau maire entament leur mandat

On Monday evening, November 24, 2025, the mayor and eight members of Côte Saint-Luc city council were formally sworn into office at a modest...

Pablo Rodriguez gave us hope and then the Quebec Liberal Party imploded; can they bounce back?

The province of Quebec has never been in worse hands than the CAQ government. Premier François Legault does indeed seem to be the captain...

David Tordjman has won the Côte Saint-Luc election for mayor

Across Quebec, including of course Côte Saint-Luc, municipal elections were held on Sunday, November 2. Lior Azerad in District 5 and...

1 COMMENT

  1. Americans will have to have a civil war or revolution based on poverty like in France or Russia before such an extreme system as has developed becomes tabu (like a strong currency is aboslutely necessary in Germany due to perceptiopn of inflation bringing down Weimar Republic for example).

Comments are closed.