Work is about to begin by Hydro-Québec on Marc Chagall Avenue, closer to Mackle Road, connected to phase two of the Equinoxe high rise building project. As a result, for the next several weeks only one lane of traffic will be available in front of the new facility.
This electrical work being performed by Hydro and their sub contractor was originally supposed to start three weeks ago, but there were unforeseen delays on their part. This work is essential for the new project and must take place before our Urban Development Department issues a building permit for the next phase.
Hydro obtained all the necessary required permits and Urban Development signed off on the signage plan and traffic lane reduction, all essential to do the required work. We were told the work could last approximately three weeks, however their intention is to complete it as fast as possible weather permitting.
We all recognize this is yet another unavoidable inconvenience for residents. It is our intent to do everything possible to minimize the problems.